Park Project Status Update

Park Project Status Update

July 24, 2026 Update Mira Mesa Community Park Phase 2 Improvements: The project has reached approximately 89% completion. Ongoing Work: Ongoing installation of site bleachers. Ongoing prep work for pool plastering and fill. Ongoing AC placement for parking lot...